SN Project Name Length (in km) Project Value (in Crore) Consultant Contractor Start Date Likely Completion Date
21 Lohara-Rengadabri-Junapani-Chouki 41.983 97.03 M/s MSV International Pvt. Ltd. M/s R.K. InfracorpPvt. Ltd. -M/s Raipur Construction Pvt. Ltd. (JV) 06 May 2017 02 Sep 2018
22 Chilphi-Rengakhar-Salhewara 60.80 137.56 Null M/s Gannon Dunkerly& Co. Ltd. 03 Jun 2017 04 Dec 2018
23 Urga-Hati 46.704 97.03 Null M/s BLA Projects Pvt. Ltd. - RK Transport & Construction Pvt. Ltd. (JV) 11 Aug 2017 08 Dec 2018
24 Seepat-Baloda-Urga 41.26 90.73 Null M/s TirupatiBuildconPvt. Ltd. & M/s Sunil Kumar Agrawal (JV) 21 Jul 2017 17 Nov 2017
25 Ambikapur Ring Road 10.80 70.60 Null M/s Shrikishan& Company 20 Jul 2017 19 Jul 2018
26 Four lane road Fafadih-Telibhandha-Naya Raipur Narrow Gauge Railway Track 12.02 258.11 M/s Lion Engineering Consultants M/s IRON TRIANGLE LIMITED 11 Apr 2017 08 Aug 2018